Make Gantt charts from text

Mar 1Mar 1Mar 8Mar 8Mar 15Mar 15Haul OutHull RepairsProvision StoresRepaint HullShip Refit Haul Out Hull Repairs Provision Stores Repaint Hull
Mar 1Mar 1Mar 8Mar 8Mar 15Mar 15Haul OutHull RepairsProvision StoresRepaint HullShip Refit Haul Out Hull Repairs Provision Stores Repaint Hull
gantt Ship Refit
start-date 2026-03-02

Haul Out 5bd
Hull Repairs 10bd
  -> Repaint Hull 4bd
Provision Stores 6bd

That is a whole gantt chart. A title line, the date the project starts, and one line per task: a name and a duration. Tasks written at the same level run in parallel; an indented -> line makes a task wait for the one above it. Everything else in this guide — groups, tags, milestones, eras, the critical path — is optional decoration on that shape. See Complete Example for what a fully dressed schedule looks like.

Dates — gantt accepts any date format (2024-01-15, 1/15, Jan 15) for start-date, task start:, eras, markers, and holidays. Add a year 2024 line to write the year just once. See Writing Dates.

Overview

Lays tasks along a timeline as bars, with dependencies, milestones, and a critical path — the standard for project scheduling and tracking. Reach for it for project schedules and timelines, task dependencies and milestones, or tracking progress against a plan. A gantt bar asserts a known start and end date; tasks run in parallel by default, chain with arrow dependencies, and the dates and critical path are calculated for you.

When to use

  • gantt — you know your dates (or your durations), and you want the schedule: what starts when, what blocks what, what’s on the critical path.
  • pert — your estimates are genuinely uncertain and the question is what could slip. Gantt bars project false precision on guessed dates; pert exists to carry three-point estimates, slack, and P50/P80/P95.
  • kanban — only what stage each item is in matters, not when it happens. Kanban needs no dates.
  • timeline — you’re recording what already happened rather than planning work with dependencies.
  • countdown — there’s one date and the only question is how long is left, not a task list.
  • goal — you want a single ”% there” reading rather than the task list and dates behind it.
  • version-control — the parallel tracks are branches that split and rejoin. That’s topology, not a calendar; gantt places work on real dates.

Basic Syntax

gantt Chart Title
start-date 2024-01-15

Task Name 30bd
Another Task 10d

The first line declares the chart type and optional title. start-date sets the project start date. Each task line has a name followed by a duration.

Duration Units

UnitMeaning
dCalendar days
bdBusiness days
wWeeks
mMonths
qQuarters
yYears
hHours
minMinutes
spSprints

The sp unit activates sprint mode automatically. See the Settings section for sprint configuration.

Groups

Groups organize tasks into labeled sections using bracket syntax. Metadata on a group is inherited by all tasks inside it:

[Shipyard] c: Sailors
  Hull Repairs 30bd
  Rigging Overhaul 10bd

[Provisions] c: Navigators
  Supply Run 15bd
  Cargo Loading 10bd

Groups can be nested:

[Ship]
  [Hull]
    Caulking 10bd
    Planking 15bd
  [Rigging]
    Mast Stepping 5bd

Scheduling Model

Bare siblings are parallel. Tasks at the same indent level inside a group start at the same time:

[Shipyard]
  Hull Repairs 30bd
  Cannon Mounting 5bd
  Deck Sealing 5bd

All three tasks above start together.

Arrows create sequential dependencies. Use -> to chain tasks so the next one starts after the previous finishes:

[Muster]
  Crew Assembly 10bd
  -> Set Sail 0d

“Set Sail” starts after “Crew Assembly” finishes.

Dependencies

Basic arrow

Indent an arrow line under a task to define a successor:

[Tavern]
  Recruit Crew 10bd
    -> Training Drills 5bd

“Training Drills” starts after “Recruit Crew” finishes.

Cross-group references

Reference a task in another group with [Group].Task:

[Shipyard]
  Rigging Overhaul 10bd
    -> [Provisions].Cargo Loading

[Provisions]
  Cargo Loading 10bd

When the target already exists elsewhere, omit the duration to create a reference-only dependency (no new task is created).

Lag (delay after predecessor)

Add a duration before the arrow to insert a gap:

  Rigging Overhaul 10bd
    -5bd-> [Provisions].Cargo Loading

“Cargo Loading” starts 5 business days after “Rigging Overhaul” finishes.

Lead (overlap with predecessor)

Double the dash to create lead time (negative lag):

  Design Review 5bd
    --2w-> Implementation 10bd

“Implementation” starts 2 weeks before “Design Review” finishes.

Offset Prefix

Prefix a task or group with +Nunit to offset it from the chart start date:

+8bd Chart New Routes 10bd
+2w [Scouting]
  Recon Harbors 5bd

“Chart New Routes” starts 8 business days after the chart start. The entire “Scouting” group starts 2 weeks after chart start.

Milestones

A task with 0d duration renders as a diamond milestone marker:

Set Sail 0d
Release Day 0d

Uncertain Duration

Append ? to the duration unit to indicate an estimate. The bar fades out over its last 20%:

Rigging Overhaul 10bd?
Treasure Hunt 30d?

The ? is a visual hedge, not a model. The bar still occupies one definite span, the dependent tasks still start on one definite date, and the critical path is still computed as if the number were certain. It is the right tool for “this one is a bit soft” on a schedule that is otherwise known.

If your estimates are genuinely uncertain — if the real question is how much the project could slip — use pert instead. PERT carries three-point estimates (optimistic / most likely / pessimistic), computes slack per task, and reports P50/P80/P95 completion dates. A gantt chart of guessed durations publishes a confident-looking schedule that nobody has any basis for believing.

Progress

Track completion with progress: metadata (0-100):

Hull Repairs 30bd progress: 80
Supply Run 15bd progress: 100

A filled overlay shows how much of the task is complete.

Tags

Tag groups categorize tasks with color-coded values. Define a block with tag Name as alias, then reference tags in task metadata using the alias:

tag Crew as c
  Sailors blue
  Navigators purple
  Lookouts orange

[Shipyard] c: Sailors
  Hull Repairs 30bd
  Cannon Mounting 5bd c: Lookouts

The first entry in a tag group is the default. Group-level tags are inherited by child tasks unless overridden.

Eras and Markers

Eras shade a background region across a time range. Markers draw a vertical line at a single date. Both accept an optional trailing color:

era 2024-01-15 -> 2024-02-15 Harbor Preparations
era 2024-03-10 -> 2024-03-14 Storm Season purple
marker 2024-02-26 Admiral Inspection
marker 2024-04-08 Landfall orange

Eras and markers also support block syntax for multiple entries:

era
  2024-01-15 -> 2024-02-15 Harbor Preparations
  2024-03-10 -> 2024-03-14 Storm Season purple

marker
  2024-02-26 Admiral Inspection
  2024-04-08 Landfall orange

Holidays and Workweek

Define non-working days inside a holiday block. Business day durations (bd) automatically skip holidays and non-workdays:

holiday
  1718-12-25 Christmas
  1718-12-31 -> 1719-01-01 New Year

workweek sun-thu

The default workweek is Mon-Fri. Override with workweek using a day range (sun-thu) or comma-separated days (mon, tue, wed, thu).

Swimlane Mode

Use lane-by GroupName to reorganize the chart into horizontal swimlanes grouped by tag value:

lane-by Crew

tag Crew as c
  Sailors blue
  Navigators purple

[Shipyard] c: Sailors
  Hull Repairs 30bd
[Navigation] c: Navigators
  Chart Routes 10bd

Each tag value gets its own collapsible lane. It’s named lane-by rather than swimlane because swimlane is its own chart type. sort tag:GroupName is an accepted back-compat spelling of the same thing. This directive is persisted from the app’s swimlane picker, so it lives in the source and every renderer honors it. In the app, click the swimlane icon on a tag pill to switch between swimlane groups.

Settings

SettingDescriptionDefault
start-dateProject start date (YYYY-MM-DD)Today
today-markerShow today marker (bare keyword or YYYY-MM-DD)off
critical-pathHighlight the critical pathoff
no-dependenciesHide dependency arrowsshown
sortTask layout: tag or tag:GroupName for swimlanesdefault
active-tagGroup to color by (first declared is active by default; none suppresses)first group
fill-solidRender bars at full saturation instead of 25% tintoff
no-titleSuppress the chart banner titleoff
sprint-lengthSprint duration (2w, 10d)2w
sprint-numberWhich sprint the chart starts at1
sprint-startDate that sprint-number begins (YYYY-MM-DD)chart start

Settings are bare keywords (no colons). Boolean settings toggle on by writing the keyword and off with no- prefix (e.g., no-dependencies).

Sprint Mode

Sprint mode activates automatically when any task uses the sp duration unit, or explicitly via sprint-* settings:

gantt Pirate Sprint Raid
start-date 2026-03-01
sprint-length 2w
sprint-number 5
sprint-start 2026-01-05

[Scouts]
  Recon Harbors 2sp
  Map Defenses 1sp

Comments

Lines starting with // are ignored. Comments can appear at the top level or indented under a task:

[Shipyard]
  Hull Repairs 30bd
  // Blocked until dry dock is available
  Rigging Overhaul 10bd

Common mistakes

Writing a date into the task name

A task line is Name then duration. The duration is read from the last token, and everything before it becomes the name — so a bare date in the middle is absorbed into the name and changes nothing about the schedule:

Provision Ship 2026-03-01 5d

That creates a task literally named Provision Ship 2026-03-01, starting at the chart start date, not in March. It validates clean — nothing warns you. The tell is the task label on the rendered bar and a timeline that begins on the wrong date.

To pin a task to a real date, use the full key-value form, where both the duration and the start are named:

Provision Ship duration: 5d, start: 2026-03-01

Mixing the two forms does not work: in Provision Ship 5d start: 2026-03-01 the 5d is absorbed into the name. Either write both keys, or use the offset prefix (+2m Provision Ship 5d) to place the task relative to the chart start.

Publishing guesses as a schedule

A gantt bar asserts a definite start and end. The ? suffix fades the bar’s tail but changes no arithmetic — dependent tasks and the critical path are still computed as if the number were certain. If the real question is how much could this slip, use pert, which carries three-point estimates and reports P50/P80/P95. See Uncertain Duration.

Trailing comments on a task line

Comments are full-line only. A // placed after content is absorbed into the value rather than stripped:

// Blocked until the dry dock frees up
Hull Repairs 30bd

Complete Example

FebFebMarMarAprAprHarbor PreparationsStorm…Admiral InspectionLandfallTodayShipyard 88%Hull RepairsCannon MountingSupply RunRigging OverhaulDeck SealingVoyage 19%Open Water RunStorm WatchDaily DrillsMutiny DrillLandfallRecon BeachGuard CampDig TreasureLoad HoldVoyage to Treasure IslandCrewSailorsNavigatorsLookoutsGroup by Crew▼ Shipyard 88% Hull Repairs Cannon Mounting Supply Run Rigging Overhaul Deck Sealing▼ Voyage 19% Open Water Run Storm Watch Daily Drills Mutiny Drill▼ Landfall Recon Beach Guard Camp Dig Treasure Load Hold Set Sail
FebFebMarMarAprAprHarbor PreparationsStorm…Admiral InspectionLandfallTodayShipyard 88%Hull RepairsCannon MountingSupply RunRigging OverhaulDeck SealingVoyage 19%Open Water RunStorm WatchDaily DrillsMutiny DrillLandfallRecon BeachGuard CampDig TreasureLoad HoldVoyage to Treasure IslandCrewSailorsNavigatorsLookoutsGroup by Crew▼ Shipyard 88% Hull Repairs Cannon Mounting Supply Run Rigging Overhaul Deck Sealing▼ Voyage 19% Open Water Run Storm Watch Daily Drills Mutiny Drill▼ Landfall Recon Beach Guard Camp Dig Treasure Load Hold Set Sail
gantt Voyage to Treasure Island
start-date 2024-01-15
today-marker 2024-03-01
critical-path

tag Crew as c
  Sailors blue
  Navigators purple
  Lookouts orange

tag Phase as p
  Outfitting green
  Voyage orange

era 2024-01-15 -> 2024-02-15 Harbor Preparations
era 2024-03-10 -> 2024-03-14 Storm Season purple
marker 2024-02-26 Admiral Inspection
marker 2024-04-08 Landfall orange

[Shipyard] c: Sailors, p: Outfitting
  Hull Repairs 18bd progress: 100
    -> Rigging Overhaul 7bd? progress: 100
  Cannon Mounting 8bd c: Lookouts, progress: 100
    -> Deck Sealing 5bd c: Lookouts, progress: 80
  Supply Run 20bd c: Navigators, progress: 70

+25bd [Voyage] c: Sailors, p: Voyage
  Chart New Routes 8bd c: Navigators, progress: 60
    -> Open Water Run 20bd progress: 15
  Storm Watch 25bd? c: Lookouts, progress: 25
  Daily Drills 18bd progress: 20
    -> Mutiny Drill 3bd? progress: 0

+55bd [Landfall] c: Lookouts, p: Voyage
  Recon Beach 3bd
    -> Dig Treasure 6bd c: Sailors
      -> Load Hold 4bd c: Sailors
        -> Set Sail 0d
  Guard Camp 9bd

Appearance

Every chart accepts the universal appearance directives:

DirectiveEffect
fill-tintSoft tinted fills (default).
fill-solidSaturated solid fills.
fill-outlineOutline only, no fill.
no-titleHide the title line.
no-legendHide the legend.

Colors come from the active palette — see Colors. Set the palette and light/dark theme at render time with --palette <name> and --theme light|dark|transparent.